August 18, 2008

Hwy A and JJ opening delayed

The construction of the roundabout at Cty Hwy JJ and A is taking longer than expected. The intersection, originally scheduled for completion in early September, will remain closed until early October, according to Outagamie County Highway Commissioner Al Guerts. The delay is caused by unexpected bedrock found throughout the soil. . Blasting is needed in order to install new sewer lines on Hwy A, slowing the entire project down.