I've had requests for a cost breakdown of the fire station. This is public information and available at the town hall. The project is capped at the $4.496 million amount. If you, or someone you know would like to bid on this project, contact the Town Hall for more information.

Formatting here does not allow for tables, so please excuse the alignment issues.

Estimates
Building Construction Costs
Excavation & Backfill $ 109,000.00
Temporary Fencing $ 12,000.00
Concrete $ 283,146.00
Rebar Material $ 35,000.00
Precast Concrete $ 16,100.00
Masonry $ 327,150.00
Miscellaneous Steel $ 82,001.00
Carpentry $ 111,722.00
Joint Sealing $ 25,000.00
HM Frames/Doors/Hdwe $ 72,868.00
Overhead & Coiling Doors $ 58,000.00
Aluminum Doors/Wdws/Glazing $ 46,250.00
Drywall/Studs/Building Insulation $ 156,100.00
Tile $ 19,800.00
Acoustical Ceilings $ 28,000.00
Carpet/Vinyl/Athletic Flooring $ 45,244.00
Painting $ 50,000.00
Specialties $ 37,934.00
Lockers $ 26,815.00
Operable Partition $ 19,440.00
Main Entry Canopy Allowance $ 55,000.00
Pre-Engineered Metal Building Frame $ 400,000.00
Plumbing $ 100,000.00
Fire Protection $ 37,500.00
HVAC $ 375,000.00
Electrical $ 300,000.00
General Conditions $ 348,530.00
CM Services $ 135,400.00
Subtotal $ 3,313,000.00

CM Fee $ 93,000.00
Building Construction Subtotal: $ 3,406,000.00


Other Project costs
Site Utilities $ 25,000.00
Asphalt Paving $ 80,000.00
Site Paving/Concrete $ 75,000.00
Landscaping $ 25,000.00
Plymovent Exhaust System $ 150,000.00
Furniture/Fixtures/Equipment $ 145,000.00
Electric Generator $ 70,000.00
Technology $ 120,000.00
Architectural and Engineering Fees $ 300,000.00
GCFS Owner Contingency $ 100,000.00
GCFS Subtotal: $ 1,090,000.00

Total Project Cost: $ 4,496,000.00